planning:refurbishment_with_passive_house_components:practical_implementations_of_step_by_step_retrofit_to_enerphit_standard
Differences
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revisionLast revisionBoth sides next revision | ||
planning:refurbishment_with_passive_house_components:practical_implementations_of_step_by_step_retrofit_to_enerphit_standard [2016/03/10 17:42] – kdreimane | planning:refurbishment_with_passive_house_components:practical_implementations_of_step_by_step_retrofit_to_enerphit_standard [2016/03/22 13:44] – kdreimane | ||
---|---|---|---|
Line 21: | Line 21: | ||
\\ Despite successful examples, the EnerPHit standard is still seen by many building owners as a challenge. The EuroPHit case studies aim to provide pragmatic answers, removing barriers one by one. | \\ Despite successful examples, the EnerPHit standard is still seen by many building owners as a challenge. The EuroPHit case studies aim to provide pragmatic answers, removing barriers one by one. | ||
- | [{{ : | + | [{{ : |
**3.1 Investment** | **3.1 Investment** | ||
\\ The first barrier is the amount of investment required: if the owner can’t invest the total budget needed for envelope and building services, then they can invest step-by-step. In several EuroPHit case studies, the investment will be spread over two steps: energy efficiency finished before 2016, then renewable energy (solar thermal and/or photovoltaics) scheduled by 2020 or 2025. Other case studies will focus first on the thermal envelope and mechanical ventilation with heat recovery, before refurbishing hot water, heating and electricity. Costs associated with asbestos or fire protection should be treated as unavoidable costs as they have no impact on the economic efficiency of an EnerPHit rehabilitation [Ebel 2014]. They must still be carefully studied as asbestos removal for example, can cost up to €15000 per dwelling. | \\ The first barrier is the amount of investment required: if the owner can’t invest the total budget needed for envelope and building services, then they can invest step-by-step. In several EuroPHit case studies, the investment will be spread over two steps: energy efficiency finished before 2016, then renewable energy (solar thermal and/or photovoltaics) scheduled by 2020 or 2025. Other case studies will focus first on the thermal envelope and mechanical ventilation with heat recovery, before refurbishing hot water, heating and electricity. Costs associated with asbestos or fire protection should be treated as unavoidable costs as they have no impact on the economic efficiency of an EnerPHit rehabilitation [Ebel 2014]. They must still be carefully studied as asbestos removal for example, can cost up to €15000 per dwelling. | ||
Line 38: | Line 39: | ||
Another option would be to reuse the existing extract system, insert an air/water heat pump on the exhaust air to generate heating and domestic hot water. This option is less efficient than a ventilation system with an air/air heat exchanger, but it is potentially cheaper. Dynamic simulations have been conducted by Gustafsson and Dermentzis [2014] on a similar system in a single family house retrofitted to EnerPHit standard. The final energy consumption of this heat pump providing heating only, was found to be around 13kWh/ | Another option would be to reuse the existing extract system, insert an air/water heat pump on the exhaust air to generate heating and domestic hot water. This option is less efficient than a ventilation system with an air/air heat exchanger, but it is potentially cheaper. Dynamic simulations have been conducted by Gustafsson and Dermentzis [2014] on a similar system in a single family house retrofitted to EnerPHit standard. The final energy consumption of this heat pump providing heating only, was found to be around 13kWh/ | ||
- | [{{ : | + | [{{ : |
**4. Management of a step-by-step retrofit** | **4. Management of a step-by-step retrofit** | ||
\\ Keys for success in a step-by-step approach consist of: organising an overall refurbishment plan with the owner, defining acceptable intermediate states, and proving cost-efficiency. | \\ Keys for success in a step-by-step approach consist of: organising an overall refurbishment plan with the owner, defining acceptable intermediate states, and proving cost-efficiency. | ||
Line 46: | Line 47: | ||
**4.2 Acceptable intermediate states.** | **4.2 Acceptable intermediate states.** | ||
- | \\ Designers and owners are not used to retrofitting a component and anticipating the future upgrade of their neighbour. Intermediate states have to be clearly described in tender documents and clearly identified on designer sketches (Figure 5, Right).[{{ : | + | \\ Designers and owners are not used to retrofitting a component and anticipating the future upgrade of their neighbour. Intermediate states have to be clearly described in tender documents and clearly identified on designer sketches (Figure 5, Right).[{{ : |
**4.3 Prove cost-efficiency.** | **4.3 Prove cost-efficiency.** | ||
Line 53: | Line 54: | ||
The EuroPHit project is co-funded by the European Commission under the grant agreement IEE/ | The EuroPHit project is co-funded by the European Commission under the grant agreement IEE/ | ||
\\ | \\ | ||
+ | \\ | ||
**5. References** | **5. References** | ||
Line 63: | Line 65: | ||
| [Sevela, Pfluger 2014] | Energy refurbishment of heritage buildings with PHPP’s and real measurements’ feedback, 18th International Passive House Conference, Aachen, 2014 | | | [Sevela, Pfluger 2014] | Energy refurbishment of heritage buildings with PHPP’s and real measurements’ feedback, 18th International Passive House Conference, Aachen, 2014 | | ||
| [Schulz 2008] |Verglaste Balkone – eine Option für die Altbaumodernisierung?, | | [Schulz 2008] |Verglaste Balkone – eine Option für die Altbaumodernisierung?, | ||
- | |||
planning/refurbishment_with_passive_house_components/practical_implementations_of_step_by_step_retrofit_to_enerphit_standard.txt · Last modified: 2016/03/22 13:50 by kdreimane