planning:refurbishment_with_passive_house_components:practical_implementations_of_step_by_step_retrofit_to_enerphit_standard

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
Last revisionBoth sides next revision
planning:refurbishment_with_passive_house_components:practical_implementations_of_step_by_step_retrofit_to_enerphit_standard [2016/03/10 17:43] – [Practical implementations of step by-step-retrofit to EnerPHit standard] kdreimaneplanning:refurbishment_with_passive_house_components:practical_implementations_of_step_by_step_retrofit_to_enerphit_standard [2016/03/22 13:44] kdreimane
Line 21: Line 21:
 \\ Despite successful examples, the EnerPHit standard is still seen by many building owners as a challenge. The EuroPHit case studies aim to provide pragmatic answers, removing barriers one by one. \\ Despite successful examples, the EnerPHit standard is still seen by many building owners as a challenge. The EuroPHit case studies aim to provide pragmatic answers, removing barriers one by one.
  
-[{{ :picopen:u-value.png?700|Figure 2:U-value of existing wall (PHPP), global cost and NPV for ETICS retrofit Envelope}}]+[{{ :picopen:u-value.png?700|Figure 2: U-value of existing wall (PHPP), global cost and NPV for ETICS retrofit Envelope}}] 
 **3.1 Investment** **3.1 Investment**
 \\ The first barrier is the amount of investment required: if the owner can’t invest the total budget needed for envelope and building services, then they can invest step-by-step. In several EuroPHit case studies, the investment will be spread over two steps: energy efficiency finished before 2016, then renewable energy (solar thermal and/or photovoltaics) scheduled by 2020 or 2025. Other case studies will focus first on the thermal envelope and mechanical ventilation with heat recovery, before refurbishing hot water, heating and electricity. Costs associated with asbestos or fire protection should be treated as unavoidable costs as they have no impact on the economic efficiency of an EnerPHit rehabilitation [Ebel 2014]. They must still be carefully studied as asbestos removal for example, can cost up to €15000 per dwelling. \\ The first barrier is the amount of investment required: if the owner can’t invest the total budget needed for envelope and building services, then they can invest step-by-step. In several EuroPHit case studies, the investment will be spread over two steps: energy efficiency finished before 2016, then renewable energy (solar thermal and/or photovoltaics) scheduled by 2020 or 2025. Other case studies will focus first on the thermal envelope and mechanical ventilation with heat recovery, before refurbishing hot water, heating and electricity. Costs associated with asbestos or fire protection should be treated as unavoidable costs as they have no impact on the economic efficiency of an EnerPHit rehabilitation [Ebel 2014]. They must still be carefully studied as asbestos removal for example, can cost up to €15000 per dwelling.
Line 53: Line 54:
 The EuroPHit project is co-funded by the European Commission under the grant agreement IEE/12/070/SI2.645928. The EuroPHit project is co-funded by the European Commission under the grant agreement IEE/12/070/SI2.645928.
 \\ \\
 +\\ 
  
 **5. References** **5. References**
Line 64: Line 66:
 | [Schulz 2008] |Verglaste Balkone – eine Option für die Altbaumodernisierung?, Protokollband Nr. 37. Passivhaus Institut, Darmstadt, 2008 | | [Schulz 2008] |Verglaste Balkone – eine Option für die Altbaumodernisierung?, Protokollband Nr. 37. Passivhaus Institut, Darmstadt, 2008 |
  
-\\ \\ 
  
 |//The sole responsibility for the content of Passipedia lies with the authors. \\ |//The sole responsibility for the content of Passipedia lies with the authors. \\
planning/refurbishment_with_passive_house_components/practical_implementations_of_step_by_step_retrofit_to_enerphit_standard.txt · Last modified: 2016/03/22 13:50 by kdreimane