planning:refurbishment_with_passive_house_components:airtightness:step-by-step_retrofit_-_airtightness_concept

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Next revision
Previous revision
planning:refurbishment_with_passive_house_components:airtightness:step-by-step_retrofit_-_airtightness_concept [2015/06/15 12:41] – created mschuerenplanning:refurbishment_with_passive_house_components:airtightness:step-by-step_retrofit_-_airtightness_concept [2015/08/04 18:05] (current) kdreimane
Line 1: Line 1:
 \\ \\
 ====== Step-by-step retrofit: Airtightness concept ====== ====== Step-by-step retrofit: Airtightness concept ======
- + {{:picopen:iee_.png?nolink |}} [[http://europhit.eu|{{:picopen:europhit_logo.png?nolink}}]] \\ \\
-{{:picopen:newco-funded-iee-horiz.jpg?250}} [[http://europhit.eu|{{:picopen:europhit_logo_122x46.png?150}}]] \\ \\+
  
 **Author: Soeren Peper**  **Author: Soeren Peper** 
Line 12: Line 11:
 For the Tevesstrasse project in Frankfurt am Main (multi-storey building with a total of 53 apartments), which was refurbished using Passive House components, a comparison of the airtightness values measured before and after the modernisation measures demonstrated the effectiveness of the concept developed at an early stage and its successful implementation. Comparison of the airtightness values in Figure 1 shows an improvement by a factor of 10: the average value of 4.4 has been reduced to 0.46 h<sup>-1</sup>. This illustrates the huge progress made in the area of the airtight envelope in these buildings. In this refurbishment, besides the systematic improvement of the building envelope, this was in part due to the fact that there were no longer any air vents in the kitchens, which have previously been used for supplying air to the coal burning stoves. For the Tevesstrasse project in Frankfurt am Main (multi-storey building with a total of 53 apartments), which was refurbished using Passive House components, a comparison of the airtightness values measured before and after the modernisation measures demonstrated the effectiveness of the concept developed at an early stage and its successful implementation. Comparison of the airtightness values in Figure 1 shows an improvement by a factor of 10: the average value of 4.4 has been reduced to 0.46 h<sup>-1</sup>. This illustrates the huge progress made in the area of the airtight envelope in these buildings. In this refurbishment, besides the systematic improvement of the building envelope, this was in part due to the fact that there were no longer any air vents in the kitchens, which have previously been used for supplying air to the coal burning stoves.
  
-[{{ :playground:playground:ttt:comparison_of_measured_values_for_airtightness.png?700 |Figure 1: Comparison of measured values for airtightness in the 10 entrance stairways before and after the refurbishment of the buildings in Tevesstrasse in Frankfurt a.M. [Kaufmann et al. 2009]}}]+[{{ :picopen:comparison_of_measured_values_for_airtightness.png  |Figure 1: Comparison of measured values for airtightness in the 10 entrance stairways before and after the refurbishment of the buildings in Tevesstrasse in Frankfurt a.M. [Kaufmann et al. 2009]}}]
  
 The importance of developing a concept for airtightness at an early stage of step-by-step modernisation will be explained here using an example.  The importance of developing a concept for airtightness at an early stage of step-by-step modernisation will be explained here using an example. 
Line 20: Line 19:
 The detached house in Zellingen near Würzburg (Bavaria) was built in 1959. The size of the heated living area is 126 m². The first modernisation step took place in 1999 with extensive refurbishment of the roof, window replacement, and renovation of the bathrooms and flooring. Among other things, insulation on rafters was implemented using aluminium-coated insulation panels and the roof covering was renewed. The original windows were replaced with double glazed PVC windows. The next step of the modernisation was carried out in 2014 with extensive insulation of the building (EIFS) and the installation of a solar thermal system and a ventilation system with heat recovery. The third step of the modernisation will take place in the next few years with the substitution of the windows with products of a high thermal quality. The renewal of the windows has already been taken into account currently by affixing a wooden construction around the windows, into which the new windows will be mounted in the centre of the insulation layer in an optimal way without damaging the thermal insulation. The detached house in Zellingen near Würzburg (Bavaria) was built in 1959. The size of the heated living area is 126 m². The first modernisation step took place in 1999 with extensive refurbishment of the roof, window replacement, and renovation of the bathrooms and flooring. Among other things, insulation on rafters was implemented using aluminium-coated insulation panels and the roof covering was renewed. The original windows were replaced with double glazed PVC windows. The next step of the modernisation was carried out in 2014 with extensive insulation of the building (EIFS) and the installation of a solar thermal system and a ventilation system with heat recovery. The third step of the modernisation will take place in the next few years with the substitution of the windows with products of a high thermal quality. The renewal of the windows has already been taken into account currently by affixing a wooden construction around the windows, into which the new windows will be mounted in the centre of the insulation layer in an optimal way without damaging the thermal insulation.
  
-[{{ :playground:playground:ttt:modernised_detached_house_in_zellingen.png?700 |Figure 2: Modernised detached house in Zellingen near Würzburg (Bavaria), with a renewed roof (left) and after a further modernisation step (right). Photos © Passive House Institute}}]  +[{{ :picopen:modernised_detached_house_in_zellingen.png?700 |Figure 2: Modernised detached house in Zellingen near Würzburg (Bavaria), with a renewed roof (left) and after a further modernisation step (right). Photos © Passive House Institute}}]  
 The roof area of the building was timber-cladded on the inside. This was also the reason why the decision for insulation on the roof was made for the roof renewal in 1999. This measure could be carried out completely from the outside without any problems. A concept for airtightness was not developed at the time, and the subject of airtightness was not considered any further. The aluminium-coated insulation panels were laid using a tongue-and-groove system without any other airtight sealing between these. Since airtightness was not tested after the installation, the issue of the lack of sealing could not be addressed. The roof area of the building was timber-cladded on the inside. This was also the reason why the decision for insulation on the roof was made for the roof renewal in 1999. This measure could be carried out completely from the outside without any problems. A concept for airtightness was not developed at the time, and the subject of airtightness was not considered any further. The aluminium-coated insulation panels were laid using a tongue-and-groove system without any other airtight sealing between these. Since airtightness was not tested after the installation, the issue of the lack of sealing could not be addressed.
-[{{ :playground:playground:ttt:the_aluminium-coated_insulation.png?700 |Figure 3: Roof area with the existing timber cladding (left). The aluminium-coated insulation panels can be seen after the removal of the cladding (right). Photos © Passive House Institute}}]+[{{ :picopen:the_aluminium-coated_insulation.png?700 |Figure 3: Roof area with the existing timber cladding (left). The aluminium-coated insulation panels can be seen after the removal of the cladding (right). Photos © Passive House Institute}}]
 The subject of airtightness became relevant with the next modernisation step in the year 2014. No changes were planned for the already renewed roof. In order to improve airtightness of the roof space, the timber cladding of the roof area was almost entirely removed on the inside. The aluminium-coated insulation panels served as the airtight layer. An attempt was made to seal the joints between the panels using adhesive tape and a sprayed-on compound. The subject of airtightness became relevant with the next modernisation step in the year 2014. No changes were planned for the already renewed roof. In order to improve airtightness of the roof space, the timber cladding of the roof area was almost entirely removed on the inside. The aluminium-coated insulation panels served as the airtight layer. An attempt was made to seal the joints between the panels using adhesive tape and a sprayed-on compound.
 However, sealing could not be implemented at the regularly-occurring points where the insulation panels rested on the rafters because the panels could not be raised. All these points represented leaks. The attempt to seal the panels all around alongside the rafters (on both sides) significantly extends the sealing surface by several times. In addition, the problem was shifted from the annexe and entrance area to the inaccessible connection points at the eaves, partly at the roof ridge and the junction of the main roof with the roof of the entrance porch. The leakage area could be reduced through work involving a lot of time and resources, but permanent and adequate airtightness could not really be achieved in this way.  However, sealing could not be implemented at the regularly-occurring points where the insulation panels rested on the rafters because the panels could not be raised. All these points represented leaks. The attempt to seal the panels all around alongside the rafters (on both sides) significantly extends the sealing surface by several times. In addition, the problem was shifted from the annexe and entrance area to the inaccessible connection points at the eaves, partly at the roof ridge and the junction of the main roof with the roof of the entrance porch. The leakage area could be reduced through work involving a lot of time and resources, but permanent and adequate airtightness could not really be achieved in this way. 
 The following figures show the leaks and the extremely complicated efforts made for sealing, which were only partially successful. The following figures show the leaks and the extremely complicated efforts made for sealing, which were only partially successful.
-[{{ :playground:playground:ttt:subsequent_sealing_of_the_connection.png?700 |Figure 4: Left: Subsequent sealing of the connection between two aluminium-coated insulation panels using joint adhesive is only possible between the rafters. Right: Sealing in the area of the roof ridge and gable wall using additional elaborately adapted OSBs which were sealed using adhesive tape and adhesive paste. Photos © Passive House Institute}}]+[{{ picopen:subsequent_sealing_of_the_connection.png?700 |Figure 4: Left: Subsequent sealing of the connection between two aluminium-coated insulation panels using joint adhesive is only possible between the rafters. Right: Sealing in the area of the roof ridge and gable wall using additional elaborately adapted OSBs which were sealed using adhesive tape and adhesive paste. Photos © Passive House Institute}}]
  
  
  
-[{{ :playground:playground:ttt:insulation_panels_rest_on_the_old_timber_cladding_of_the_roof_overhang.png?700 |Figure 5: Left: At the edge of the roof the insulation panels rest on the old timber cladding of the roof overhang on the gable side. Leaks were detected along the entire length of the connection to the insulation panel alongside the sawn-off wooden boards (left). Efforts to seal this subsequently were only partially successful.  +[{{ :picopen:insulation_panels_rest_on_the_old_timber_cladding_of_the_roof_overhang.png?700 |Figure 5: Left: At the edge of the roof the insulation panels rest on the old timber cladding of the roof overhang on the gable side. Leaks were detected along the entire length of the connection to the insulation panel alongside the sawn-off wooden boards (left). Efforts to seal this subsequently were only partially successful.  
 Right: elaborate sealing of the floor in the tip of the roof slope plus additional poured gypsum plaster. Photos © Passive House Institute}}] Right: elaborate sealing of the floor in the tip of the roof slope plus additional poured gypsum plaster. Photos © Passive House Institute}}]
 Double floors with openings towards the attic existed in some attic areas. At negative pressure, massive air flows passed through these openings into the attic. The point of entry on the outside was inaccessible or could not be ascertained. Supposedly this was the edge of the aluminium covered insulating panels at the eaves. As an effort was made to seal this tapered area at the transition of the attic floor to the roof from inside the roof area using boards etc. (Figure 5 / right), there was now increased air flow through this empty space. After this fault had been localised, an attempt was made to seal this leak using boards here as well (Figure 6). However, this was not completely possible on account of the interruption of the leakage surface due to the roof rafters. Double floors with openings towards the attic existed in some attic areas. At negative pressure, massive air flows passed through these openings into the attic. The point of entry on the outside was inaccessible or could not be ascertained. Supposedly this was the edge of the aluminium covered insulating panels at the eaves. As an effort was made to seal this tapered area at the transition of the attic floor to the roof from inside the roof area using boards etc. (Figure 5 / right), there was now increased air flow through this empty space. After this fault had been localised, an attempt was made to seal this leak using boards here as well (Figure 6). However, this was not completely possible on account of the interruption of the leakage surface due to the roof rafters.
-[{{ :playground:playground:ttt:double_floors.png?700 |Figure 6: Double floors with massive leakage of air flow into the attic area (at negative pressure). On the left: before sealing of this area; on the right: after sealing with a glued board. Photos © Passive House Institute}}]+[{{ :picopen:double_floors.png?700 |Figure 6: Double floors with massive leakage of air flow into the attic area (at negative pressure). On the left: before sealing of this area; on the right: after sealing with a glued board. Photos © Passive House Institute}}]
 Had a concept for airtightness been developed at an early stage, the focus would have had to be on the sealing of the roof area together with the connections to the airtight layer of the lower part of the building (existing exterior plaster). Various solutions would have been considered; a concept with the least possible penetrations should always be selected. Had a concept for airtightness been developed at an early stage, the focus would have had to be on the sealing of the roof area together with the connections to the airtight layer of the lower part of the building (existing exterior plaster). Various solutions would have been considered; a concept with the least possible penetrations should always be selected.
 In general, it is challenging when the airtight layers of different areas cannot simply be directly joined with each other. The connection of the roof area to the airtight layer of the walls of the room below – as in the present example - is typical. In such cases, good airtightness values often cannot be expected.  The schematic diagrams in Figure 7 show which of the two systematic solutions are conceivable for this in the case of a refurbishment involving wood beam ceilings. One possibility is the airtight connection "through" or "in front of" the wood beam ceiling (around the outside). For this, the sheeting can be passed directly through between the beam heads, but it must be carefully sealed around each beam. This presupposes accessibility of the entire area. The possibility shown in the figure is to airtightly "wrap" the entire ceiling space all around (in this cross-section, e.g. up to the opening for the stairs or trapdoor). This should only be implemented if sufficient wind-tightness of these areas is ensured on the outside, otherwise cold air may pass through these "facade constrictions" with large surface areas and the heat losses of the building could increase noticeably. In general, it is challenging when the airtight layers of different areas cannot simply be directly joined with each other. The connection of the roof area to the airtight layer of the walls of the room below – as in the present example - is typical. In such cases, good airtightness values often cannot be expected.  The schematic diagrams in Figure 7 show which of the two systematic solutions are conceivable for this in the case of a refurbishment involving wood beam ceilings. One possibility is the airtight connection "through" or "in front of" the wood beam ceiling (around the outside). For this, the sheeting can be passed directly through between the beam heads, but it must be carefully sealed around each beam. This presupposes accessibility of the entire area. The possibility shown in the figure is to airtightly "wrap" the entire ceiling space all around (in this cross-section, e.g. up to the opening for the stairs or trapdoor). This should only be implemented if sufficient wind-tightness of these areas is ensured on the outside, otherwise cold air may pass through these "facade constrictions" with large surface areas and the heat losses of the building could increase noticeably.
-[{{ :playground:playground:ttt:interruption_of_a_continuous_airtight_layer.png?700 |Figure 7: Interruption of a continuous airtight layer by the wood beam ceiling. For the connection between the airtight layer of the roof area and the wall area, either a connection “through” the ceiling can be chosen, or the whole roof area must be bordered air tightly from above and below, up to the opening for the stairs for example (Source: [Feist/Peper 2005]).}}]+[{{ :picopen:interruption_of_a_continuous_airtight_layer.png?700 |Figure 7: Interruption of a continuous airtight layer by the wood beam ceiling. For the connection between the airtight layer of the roof area and the wall area, either a connection “through” the ceiling can be chosen, or the whole roof area must be bordered air tightly from above and below, up to the opening for the stairs for example (Source: [Feist/Peper 2005]).}}]
  
 A third solution that is possible is to shift the airtight layer to the outside of the building. This can be done by inspecting and reinforcing of the old plaster if necessary, or by applying filler. However, this only makes sense if thermal insulation is applied afterwards as soon as possible, in order to protect this layer permanently from thermal stresses (formation of cracks). This airtight layer on the old exterior surface must then be consistently connected at all relevant points (base point of the building and roof to attic transition). A third solution that is possible is to shift the airtight layer to the outside of the building. This can be done by inspecting and reinforcing of the old plaster if necessary, or by applying filler. However, this only makes sense if thermal insulation is applied afterwards as soon as possible, in order to protect this layer permanently from thermal stresses (formation of cracks). This airtight layer on the old exterior surface must then be consistently connected at all relevant points (base point of the building and roof to attic transition).
Line 45: Line 44:
 In the building there was an installation shaft which connected the basement with the attic floor (see Figure 8). Cables passed through this shaft and since the modernisation, also the supply lines for the solar heating system. Because the basement was situated outside of the airtight envelope, the shaft represented a potential leakage therefore it had to be sealed airtightly.  In the building there was an installation shaft which connected the basement with the attic floor (see Figure 8). Cables passed through this shaft and since the modernisation, also the supply lines for the solar heating system. Because the basement was situated outside of the airtight envelope, the shaft represented a potential leakage therefore it had to be sealed airtightly. 
  
-[{{ :playground:playground:ttt:shaft_from_the_basement_to_the_attic_floor.png?700 |Figure 8: Shaft from the basement to the attic floor of the building for routing pipes and electrical cables.  © Passive House Institute}}]+[{{ :picopen:shaft_from_the_basement_to_the_attic_floor.png?700 |Figure 8: Shaft from the basement to the attic floor of the building for routing pipes and electrical cables.  © Passive House Institute}}]
 In practice, this was not easy to do because of restricted accessibility and the different materials etc. Pouring with thin plaster or expanding mortar proved to be a good solution (Figure 9). Before using this, the shaft had to be stuffed with construction foam so that the plaster or mortar did not drain away downwards, and a plug was formed. All cavities and spaces as well as the areas between cables and wires are filled completely due to the thinness of the plaster. In practice, this was not easy to do because of restricted accessibility and the different materials etc. Pouring with thin plaster or expanding mortar proved to be a good solution (Figure 9). Before using this, the shaft had to be stuffed with construction foam so that the plaster or mortar did not drain away downwards, and a plug was formed. All cavities and spaces as well as the areas between cables and wires are filled completely due to the thinness of the plaster.
-[{{ :playground:playground:ttt:intersection_of_two_pipes_and_cables.png?700 |Figure 9: Attic floor: intersection of two pipes and cables in the shaft towards the basement (left: without further sealing (7.2.2014); right: poured entry point (31.3.2014). Photos © Passive House Institute}}] +[{{ :picopen: intersection_of_two_pipes_and_cables.png?700 |Figure 9: Attic floor: intersection of two pipes and cables in the shaft towards the basement (left: without further sealing (7.2.2014); right: poured entry point (31.3.2014). Photos © Passive House Institute}}] 
-[{{ :playground:playground:ttt:basement_shaft_with_solar_lines_and_cables.png?700 |Figure 10: Basement: shaft with solar lines and cables leading towards the attic floor. The "undefined" edges of the end of the shaft in the basement ceiling are clearly visible. Photos © Passive House Institute }}]+[{{ :picopen: basement_shaft_with_solar_lines_and_cables.png?700 |Figure 10: Basement: shaft with solar lines and cables leading towards the attic floor. The "undefined" edges of the end of the shaft in the basement ceiling are clearly visible. Photos © Passive House Institute }}]
 In another area of the basement, there was a second shaft end with more lines towards the first floor (Figure 11). The same situation existed here with reference to airtightness.  In another area of the basement, there was a second shaft end with more lines towards the first floor (Figure 11). The same situation existed here with reference to airtightness. 
 When preparing the concept for airtightness, such areas should be identified early on and taken into account in the concept. Defined starting and ending points, and specification of a method for sealing will facilitate the procedure. In this way there will be no surprises during the airtightness measurement due to this leak.  When preparing the concept for airtightness, such areas should be identified early on and taken into account in the concept. Defined starting and ending points, and specification of a method for sealing will facilitate the procedure. In this way there will be no surprises during the airtightness measurement due to this leak. 
  
-[{{ :playground:playground:ttt:the_end_of_another_shaft_in_the_basement.png?700 |Figure 11: The end of another shaft in the basement through which water and drainage pipes as well as cables were routed. The construction foam (light yellow) was used here not for sealing but rather as the lower limit for the poured plaster. Photos © Passive House Institute }}]+[{{ :picopen:the_end_of_another_shaft_in_the_basement.png?700 |Figure 11: The end of another shaft in the basement through which water and drainage pipes as well as cables were routed. The construction foam (light yellow) was used here not for sealing but rather as the lower limit for the poured plaster. Photos © Passive House Institute }}]
 A typical problem arising during modernisation is the lack of clarity regarding the course of the airtight layer. In a rough concept the "pencil rule" principle must be applied, in which the uninterrupted airtight layer is clearly specified by the architect in all cross sections (Figure 12). In the ensuing detailed planning, detailed solutions with information about the materials used must be prepared for all transitions and connections. Only in this way will it be possible to ensure that solutions exist and that craftpersons are given clear instructions for executing the work. A typical problem arising during modernisation is the lack of clarity regarding the course of the airtight layer. In a rough concept the "pencil rule" principle must be applied, in which the uninterrupted airtight layer is clearly specified by the architect in all cross sections (Figure 12). In the ensuing detailed planning, detailed solutions with information about the materials used must be prepared for all transitions and connections. Only in this way will it be possible to ensure that solutions exist and that craftpersons are given clear instructions for executing the work.
-[{{ :playground:playground:ttt:the_pencil_rule.png?700 |Figure 12: The "pencil rule" is used to specify clearly the position of the airtight layer (in red here) in the cross-sections of the building. The appropriate materials for each transition must be indicated in the detailed planning (according to Peper/Feist/Sariri1999]).}}]+[{{ :picopen:the_pencil_rule.png?700 |Figure 12: The "pencil rule" is used to specify clearly the position of the airtight layer (in red here) in the cross-sections of the building. The appropriate materials for each transition must be indicated in the detailed planning (according to Peper/Feist/Sariri1999]).}}]
 \\ \\
 ==== Airtightness measurements ==== ==== Airtightness measurements ====
Line 61: Line 60:
 The first measurement was carried out for testing the sealing work. This revealed that massive leakages existed and some points had not been sealed or were inadequately sealed, or had been sealed at the wrong places. The main point of leakage was localised above the entrance area at the transition to the roof.  The first measurement was carried out for testing the sealing work. This revealed that massive leakages existed and some points had not been sealed or were inadequately sealed, or had been sealed at the wrong places. The main point of leakage was localised above the entrance area at the transition to the roof. 
  
-[{{ :playground:playground:ttt:point_of_leakage.png?700 |Figure 13: Point of leakage between the roof extension and the concrete slab above the entrance area. Photo © Passive House Institute }}]+[{{ :picopen:point_of_leakage.png?700 |Figure 13: Point of leakage between the roof extension and the concrete slab above the entrance area. Photo © Passive House Institute }}]
 Due to the low airtightness of the building during the first Blower Door measurement (n<sub>50</sub> = 8.9 h<sup>-1</sup>), further sealing work was carried out and an attempt was made to seal the large leak in the area of the roof connection in particular.  Due to the low airtightness of the building during the first Blower Door measurement (n<sub>50</sub> = 8.9 h<sup>-1</sup>), further sealing work was carried out and an attempt was made to seal the large leak in the area of the roof connection in particular. 
 The complicated sealing work was tested during the second measurement which took place two weeks later. It turned out that numerous leaks still existed despite significant improvements. The measured value was reduced by almost a half. In particular, the leaks discussed previously were identified as the biggest source of leakage: The complicated sealing work was tested during the second measurement which took place two weeks later. It turned out that numerous leaks still existed despite significant improvements. The measured value was reduced by almost a half. In particular, the leaks discussed previously were identified as the biggest source of leakage:
Line 83: Line 82:
 Using this example case and the results of the airtightness measurements and leak detection, the need for a comprehensive concept for airtightness is clearly evident.  This must be prepared at the start, before any of the modernisation measures. For this, it is necessary to have a detailed record of the current state of all relevant points, and the exact position of the airtight layer must then be specified in the concept (sketch). Finally a solution must be developed for all connections and transitions, using a detail drawing if necessary, and the materials to be used for these points and connections must be specified. Using this example case and the results of the airtightness measurements and leak detection, the need for a comprehensive concept for airtightness is clearly evident.  This must be prepared at the start, before any of the modernisation measures. For this, it is necessary to have a detailed record of the current state of all relevant points, and the exact position of the airtight layer must then be specified in the concept (sketch). Finally a solution must be developed for all connections and transitions, using a detail drawing if necessary, and the materials to be used for these points and connections must be specified.
  
-{{ :playground:playground:ttt:procedure_for_implementing.png |Figure 14: Procedure for implementing a successful airtightness concept in modernisation projects. Photo © Passive House Institute }}+[{{ :picopen:procedure_for_implementing.png |Figure 14: Procedure for implementing a successful airtightness concept in modernisation projects. Photo © Passive House Institute }}]
 \\ \\
  
Line 91: Line 90:
 ==== Literature ==== ==== Literature ====
  
-|[Feist/Peper 2005]|Feist, W; Peper, S.: 3-D-Luftdichtheitsan-schlüsse. (3-D Airtight connections) Passive House Institute, Darmstadt, 2005. Not published.| +|[Feist/Peper 2005]|Feist, W; Peper, S.: 3-D-Luftdichte Anschlüsse. (3-D Airtight Connections) Passive House Institute, Darmstadt, 2005. Not published.| 
-|[Kaufmann et al. 2009]|Berthold Kaufmann; Søren Peper; Rainer Pfluger; Wolfgang Feist: Sanierung mit Passivhaus-komponenten, Planungsbegleitende Beratung und Qualitätssicherung Tevesstraße Frankfurt a.M., Bericht im Auftrag des Hessischen Ministeriums für Wirtschaft, Verkehr und Landesentwicklung, Wiesbaden, Passivhaus Institut, Darmstadt, 2009. Download unter: www.passiv.de\\ //Refurbishment using Passive House components, consultation during planning and quality assurance for the Tevesstrasse Project in Frankfurt, Report commissioned by the Ministry of Economy, Transport and Regional Development of the German State of Hesse, Wiesbaden, Passive house Institute, Darmstadt 2009//|+|[Kaufmann et al. 2009]|Berthold Kaufmann; Søren Peper; Rainer Pfluger; Wolfgang Feist: Sanierung mit Passivhaus-Komponenten, Planungsbegleitende Beratung und Qualitätssicherung Tevesstraße Frankfurt a.M., Bericht im Auftrag des Hessischen Ministeriums für Wirtschaft, Verkehr und Landesentwicklung, Wiesbaden, Passivhaus Institut, Darmstadt, 2009. Download unter: www.passiv.de\\ //Refurbishment using Passive House components, consultation during planning and quality assurance for the Tevesstrasse Project in Frankfurt, Report commissioned by the Ministry of Economy, Transport and Regional Development of the German State of Hessen, Wiesbaden, Passive house Institute, Darmstadt 2009//|
 |[Peper/Feist/Sariri 1999]|Peper, S., Feist, W.: Luftdichte Projektierung von Passivhäusern, CEPHEUS-Projektinformation Nr. 7, Passivhaus Institut, Darmstadt, 1999; Fachinformation PHI-1999/6, 10. Auflage Oktober 2009.\\ //Airtight planning of Passive Houses, CEPHEUS Project Information No. 7, Passive House Institute, Darmstadt 1999; Technical Information PHI-1999/6, 10th edition, October 2009//| |[Peper/Feist/Sariri 1999]|Peper, S., Feist, W.: Luftdichte Projektierung von Passivhäusern, CEPHEUS-Projektinformation Nr. 7, Passivhaus Institut, Darmstadt, 1999; Fachinformation PHI-1999/6, 10. Auflage Oktober 2009.\\ //Airtight planning of Passive Houses, CEPHEUS Project Information No. 7, Passive House Institute, Darmstadt 1999; Technical Information PHI-1999/6, 10th edition, October 2009//|
 \\ \\
planning/refurbishment_with_passive_house_components/airtightness/step-by-step_retrofit_-_airtightness_concept.1434364881.txt.gz · Last modified: 2015/06/15 12:41 by mschueren