+ | ====== Airtightness test ====== | ||
+ | |||
+ | |||
+ | |||
+ | Infiltration (gap ventilation) cannot ensure a continuous and adequate exchange of air (see [[planning: | ||
+ | |||
+ | |||
+ | |||
+ | The situation in many countries can be suitably described in the following words: | ||
+ | |||
+ | **Nowadays the level of airtightness in newly constructed buildings is usually too low for damage-free envelope components, and at the same time too high to allow for sufficient gap ventilation.**\\ | ||
+ | \\ | ||
+ | |||
+ | ===== Air pressure test ===== | ||
+ | |||
+ | The **air pressure test**, or the **n< | ||
+ | \\ | ||
+ | |||
+ | |{{ : | ||
+ | |**//Blower door built into a\\ door leading to a terrace.// | ||
+ | \\ | ||
+ | |||
+ | ===== Background: German legal requirements ===== | ||
+ | |||
+ | |||
+ | In Germany, for example, a target value for new buildings was first introduced by the German Energy Saving Ordinance (EnEV) of 01.02.2001. **Specific values for the pressurisation test (n< | ||
+ | Experience with low-energy and Passive Houses has shown that better airtightness (i.e. a lower n< | ||
+ | \\ | ||
+ | |||
+ | ===== The Passive House ===== | ||
+ | |||
+ | Much better values are regularly achieved for Passive Houses: n< | ||
+ | \\ | ||
+ | |{{ : | ||
+ | |// | ||
+ | and the EnEV requirements. Nowadays, if one wishes to build a\\ | ||
+ | house, attention should be paid to a high level of airtightness\\ | ||
+ | - because trying to improve the airtightness afterwards is much more\\ | ||
+ | difficult and only possible during the course of a full\\ refurbishment.**// | ||
+ | |||
+ | ===== See also ===== | ||
+ | |||
+ | |||
+ | [[planning: | ||